Suez entrusts Micr’Eau with a preliminary study to supply two Sattler brand flexible gasometers for the Alsatian Benfeld project
Micr’Eau, with its nearly 20 years of experience with all the technical solutions developed with the Sattler group in the field of biogas storage, is entrusted by Suez France (Strasbourg agency) with detail studies of the installation of two gasometers on post digesters as part of the contract of work won by this group on behalf of the SDEA.
The objective is to size two stockers with a total volume of nearly 1000 m3 of biogas produced by the methanization of sludge from the treatment of wastewater from the Benfeld desure plant (67).
This study will result in the completion of these biogas storage works from 2021 before being injected into the grid.